Software | Used Float Types | Definition for TF | Definition for FF | Key Difference Compared to Other PMSs |
---|---|---|---|---|
Microsoft® Office Project | TF, FF, start float and finish float | The amount of time an activity’s finish date can be delayed without delaying the project’s finish date | The amount of time that an activity can be delayed without delaying any successor activity | It defines the negative total float to display the amount of negative total float for an activity on the Gantt Chart |
Oracle® Primavera® P6TM | TF, FF, start float and finish float | The amount of time the selected activity can be delayed without delaying the project’s finish date | The amount of time the selected activity can be delayed without delaying the immediate successor activities | It defines the float path to representing the path made of activities that drive the activity with the least TF/FF |
Deltek® Open PlanTM | TF, FF, finish total float, finish free float, relationship total float and relationship free float | The difference between the early and late start dates measured in working periods of the activity calendar |
The maximum amount by which an activity can be delayed beyond its early dates without delaying any successor activity beyond its early dates |
It defines the scheduled float to the difference between the late finish date and the scheduled finish date of the activity |