Table 3: Characterization of construction works investigated by [20].

Company E1 E2
Left Side Right Side Rear Facade Internal Coating
Workforce Outsourced Outsourced Outsourced Own
Number of pavements 13 21
Relation
janitor:
manson
4:3 7:1 3:1 15:3
RUPmason (Mh/m2) 0.43 a 1.44 0.52 a 1.17 0.60 a 0.76 0.61 a 0.62
Mortar type Industrialized Industrialized Industrialized Industrialized
Application method Projected Projected Projected Projected
Mix equipment Projection machine Projection machine Projection machine Mortar mixer
Mix location On pavement On pavement On pavement -
Transport equipment Rack Rack and rocker Rack -

Source: Adapted from [20].