No. |
Factor |
Mean |
Std. |
RII % |
T-test |
P-value |
Rank |
1 |
Top management support |
4.03 |
1.247 |
80.612 |
8.180 |
0.000 |
2 |
2 |
nvolvement of all stakeholders |
3.28 |
1.299 |
65.51 |
2.100 |
0.000 |
15 |
3 |
Coordination and cooperation between staffs to achieve team work |
3.94 |
1.283 |
78.776 |
7.244 |
0.000 |
3 |
4 |
Close relationship with suppliers |
3.58 |
1.354 |
71.633 |
4.252 |
0.000 |
10 |
5 |
Motivate employees to make change |
2.84 |
1.518 |
56.735 |
-1.065 |
0.000 |
16 |
6 |
Manage resistance of managers to change planner system |
3.47 |
1.548 |
69.388 |
3.002 |
0.000 |
11 |
7 |
Definition of roles and responsibilities |
3.30 |
1.487 |
65.918 |
1.970 |
0.000 |
13 |
8 |
Involvement of management staffs |
3.45 |
1.194 |
68.98 |
3.723 |
0.000 |
12 |
9 |
Increased support and monitoring of management for Subordinates |
3.70 |
1.408 |
74.082 |
4.949 |
0.000 |
8 |
10 |
Update the program daily |
3.76 |
1.393 |
75.102 |
5.368 |
0.000 |
7 |
11 |
Accuracy and flexibility in planning |
3.81 |
1.39 |
76.122 |
5.743 |
0.000 |
5 |
12 |
Greater commitment by management on the implementation of development system promises |
3.65 |
1.244 |
73.061 |
5.195 |
0.000 |
9 |
13 |
Close relationship with subcontractors |
4.05 |
1.097 |
81.02 |
9.484 |
0.000 |
1 |
14 |
Willingness to learn and train |
2.82 |
1.515 |
56.327 |
-1.200 |
0.000 |
17 |
15 |
Sufficient knowledge to start the project |
3.81 |
1.198 |
76.122 |
6.659 |
0.000 |
5 |
16 |
Sufficient knowledge for scheduling and planning |
3.83 |
1.227 |
76.531 |
6.668 |
0.000 |
4 |
17 |
Sufficient knowledge for controlling system |
3.30 |
1.487 |
65.918 |
1.970 |
0.000 |
13 |