| - | Parametric Costs (€/m2) | - | Parametric Costs (€/m2) |
|---|---|---|---|
| First Level-Entrance hall and laboratories | 1130 | Second Level-Flexible learning spaces and elementary school group learning spaces | 1100 |
| Structures | 311 | Structures | 292 |
| Vertical closures | 226 | Vertical closures | 220 |
| Horizontal closures | 113 | Horizontal closures | 110 |
| Internal partitions | 57 | Internal partitions | 99 |
| Floors and finishing works | 124 | Floors and finishing works | 132 |
| Mechanical plant | 226 | Mechanical plant | 176 |
| Electrical plant | 73 | Electrical plant | 72 |
| First Level-Dining hall (Kitchens and depositories) | 870 | Third Level-Flexible learning spaces and middle school group learning spaces | 1100 |
| Structures | 46 | Structures | 292 |
| Vertical closures | 174 | Vertical closures | 220 |
| Horizontal closures | 87 | Horizontal closures | 110 |
| Internal partitions | 61 | Internal partitions | 99 |
| Floors and finishing works | 96 | Floors and finishing works | 132 |
| Mechanical plant | 165 | Mechanical plant | 176 |
| Electrical plant | 57 | Electrical plant | 72 |
| First Level-Flexible learning spaces and nursery school group learning spaces | 1125 | Auditorium / Library (only low level) | 1130 |
| Structures | 298 | Structures | 283 |
| Vertical closures | 225 | Vertical closures | 113 |
| Horizontal closures | 113 | Horizontal closures | 85 |
| Internal partitions | 79 | Internal partitions | 0 |
| Floors and finishing works | 124 | Floors and finishing works | 136 |
| Mechanical plant | 214 | Mechanical plant | 322 |
| Electrical plant | 73 | Electrical plant | 192 |