Table 1: Parametric costs for the different levels/parts of the building.

- Parametric Costs (€/m2) - Parametric Costs (€/m2)
First Level-Entrance hall and laboratories 1130 Second Level-Flexible learning spaces and elementary school group learning spaces 1100
Structures 311 Structures 292
Vertical closures 226 Vertical closures 220
Horizontal closures 113 Horizontal closures 110
Internal partitions 57 Internal partitions 99
Floors and finishing works 124 Floors and finishing works 132
Mechanical plant 226 Mechanical plant 176
Electrical plant 73 Electrical plant 72
First Level-Dining hall (Kitchens and depositories) 870 Third Level-Flexible learning spaces and middle school group learning spaces 1100
Structures 46 Structures 292
Vertical closures 174 Vertical closures 220
Horizontal closures 87 Horizontal closures 110
Internal partitions 61 Internal partitions 99
Floors and finishing works 96 Floors and finishing works 132
Mechanical plant 165 Mechanical plant 176
Electrical plant 57 Electrical plant 72
First Level-Flexible learning spaces and nursery school group learning spaces 1125 Auditorium / Library (only low level) 1130
Structures 298 Structures 283
Vertical closures 225 Vertical closures 113
Horizontal closures 113 Horizontal closures 85
Internal partitions 79 Internal partitions 0
Floors and finishing works 124 Floors and finishing works 136
Mechanical plant 214 Mechanical plant 322
Electrical plant 73 Electrical plant 192